What the NOR says
A NOR states that the vessel has arrived at the agreed place, is in every way ready and holds free pratique where required. It is tendered by the master, often through the agent, to the party named in the charter party, with the time and place recorded.
When laytime starts
Laytime start depends on the charter party. Typical terms allow a notice period after the NOR is accepted or tendered, or start laytime when loading or discharging begins. Some charters allow NOR only within office hours or only once the vessel is at the berth.
How time is counted
- Laytime may count on all days or on working days only
- Sundays and holidays may be excepted unless used
- Weather working days exclude stoppages for rain or bad weather
- Shifting between berths, breakdowns and strikes follow the charter terms
Why the agent matters
The agent records NOR tender, acceptance, berthing, start and finish of operations and each interruption. Owners and charterers calculate laytime from these times, so an accurate Statement of Facts with the reasons for each stoppage is the main evidence in any dispute.
Good practice
- Tender the NOR as soon as the vessel is entitled and keep proof of receipt
- Write the time zone and who gave each time
- Never alter a recorded time: add a revision with the reason
- Send the signed SOF to the principal quickly
Frequently asked questions
Does the agent calculate laytime?
Often the agent only records the facts. Owners, charterers or specialist claim handlers calculate laytime, though some agents prepare a draft calculation as an extra service.
What happens if the NOR is invalid?
Depending on the charter and the law applied, laytime may not start until a valid notice is given or operations begin. This is why the details of the NOR matter.